ABB ACQ580 Manual: Pick the Right Document and Start Up Safely
Finding the right abb acq580 manual is harder than it sounds, because ABB splits the “manual” into several documents. You need the right ones for your drive variant and market before you touch a wire. This guide shows which document answers which question, then walks through install and start-up in order, with a check after each stage.
On this page
- What the ABB ACQ580 manual set contains
- Where to download the correct ACQ580 manual
- What you need before you start
- Safety first: rules from ABB’s guides
- Step-by-step: install and start up an ACQ580-01 with the manual
- Step 1: Unpack and match the drive to your ACQ580 manual
- Step 2: Reform the capacitors if the drive has been stored
- Step 3: Mount the drive
- Step 4: Check the grounding system compatibility
- Step 5: Measure insulation resistance
- Step 6: Connect power and motor cables
- Which cable sizes, fuses and torques apply to each frame?
- Step 7: Connect control cables per the ACQ580 firmware manual
- Step 8: Power up and run the First start assistant
- Step 9: Prepare for and run the motor ID run from the ACQ580 manual
- Step 10: Set up the pump control mode and protections
- How do I wire and test Safe Torque Off, and set up Modbus control?
- Which ACQ580 manual fits the -04 modules and -31?
- Common ACQ580 manual mistakes to avoid
- When something goes wrong: ACQ580 manual fault tracing and when to call for help
- Frequently asked questions
What the ABB ACQ580 manual set contains
The ACQ580 is ABB’s “drives for water” family. It runs the pump control program. So the abb acq580 manual is really a set of documents, not one book.

What is the difference between the hardware manual, firmware manual and quick guide?
The ACQ580 hardware manual covers mechanical and electrical installation and technical data. The ACQ580 firmware manual covers start-up, control panel, I/O, program features, fault tracing, fieldbus and parameters. In addition, the quick guides give a short install and start-up sequence. However, ABB supplies the hardware and firmware manuals only if you order them.
Which ACQ580 manual is for the -01, -04 or -31?
Each variant has its own documents, so pick by variant first:
- ACQ580-01: wall-mounted drive, 0.75 to 250 kW (1.0 to 350 hp).
- For the ACQ580-04: drive modules, with a hardware manual for 250 to 500 kW.
- The ACQ580-31: its own hardware manual and quick installation guides.
- Other variants: ABB lists ACQ580-PC/PD and ACQ580-C01 on separate pages.
Are there different ACQ580 guides for IEC and NEC drives?
Yes. The ACQ580-01 has one quick installation and start-up guide for global (IEC) types and another for NEC (North American) types. Before you start, check which one matches your drive.
Which ACQ580-01 documents answer which question?
| Document | What it answers | ABB code |
|---|---|---|
| Hardware manual (0.75 to 250 kW) | Mounting, wiring, technical data | 3AXD50000044862 |
| Pump control firmware manual | Start-up, parameters, faults | 3AXD50000035867 |
| Quick guide, IEC types | Short install and start-up | 3AXD50001324131 |
| Quick guide, NEC types | Short install and start-up | 3AXD50001383923 |
| Pump control quick start-up guide | Fast pump set-up | 3AXD50000048773 |
In addition, ABB lists the ACQ580-04 hardware manual as 3AXD50000048677. The ACQ580-31 hardware manual is 3AXD50000045935.
Which extra ACQ580 guides exist?
ABB also publishes guides for options. These include the UL Type 12 hood, the flange mounting kit (+C135), and the main switch and EMC filter options (+F278, +F316, +E223). There is also an R9e frame installation instruction (3AXD50001240653), a UK gland plate guide, and the ACS580/ACH580/ACQ580-PDR supplement (3AXD50001285388). The Drive composer PC tool manual is 3AUA0000094606. For US irrigation, ABB lists an ACQ580 irrigation supplement (3AXD50000885664).
Where to download the correct ACQ580 manual
Start with ABB’s own pages. Use the ABB drives documents page (www.abb.com/drives/documents), the ABB Library search for ACQ580 manuals, or the ABB Drive Document Library on ABB Now. However, the documents there are download only.
How do I match the document code to my drive?
First, read the type code on the drive nameplate. Next, open the link list for your variant, such as the ACQ580-01 or ACQ580-04 manuals link list. Then search by the document code and check the revision. Because ABB updates the link lists, they show current languages and codes.
Is the ACQ580 manual version tied to the drive’s firmware version?
Yes, to a degree. For example, one ABB firmware manual says it applies to pump control program version 2.18 and later. As a result, you should check your drive’s program version against the revision of the firmware manual you download.
How do I check the installed pump control program version?
Read it from the drive’s parameters. Group 07 holds system information, and parameter 07.05 shows the firmware version (07.04 shows the firmware name). Open the parameter list on the control panel, or read it in the Drive composer PC tool. Then compare the number with the version range printed on the first pages of the firmware manual, and download the revision that covers it.
Should I trust an ACQ580 manual copy from other websites?
Be careful. Third-party sites often show older revisions and different page counts. As a result, verify any copy against ABB’s document code before you rely on it.
What you need before you start
Gather the documents, the data and the tools first. This saves trips back to the panel later.

Which ACQ580 manual and documents to gather
- The quick guide for your variant and market (IEC or NEC).
- The hardware manual, the firmware manual and the pump control quick start-up guide.
- Motor nameplate data.
- Supply voltage and grounding system type.
- Cable and fuse selection from the hardware manual for your frame size.
- Your application: single pump, multipump IPC, level control or soft pump control.
Tools and supplies
- A quality voltage tester and a known voltage source to prove it.
- An insulation tester with a 1000 V DC range.
- A multimeter.
- The mounting template and fasteners that suit your wall.
- A hand torque tool with a Pozidriv #2 bit for IP66 cable box screws.
- A lifting device for heavy frames.
Also check the box. It holds the drive, the cable box where used, the mounting template, and manuals if you ordered them.
Safety first: rules from ABB’s guides
Only qualified electrical professionals may install or maintain these drives. ABB’s quick guide says non-qualified persons must not do this work. So keep that rule in mind through every step below.

What safety precautions does the ACQ580 manual give?
- Never work on the drive, motor cable, motor or control cables while the drive has input power.
- Isolate the drive from all dangerous voltage sources, including external power to control circuits.
- Prove the installation dead with a quality voltage tester. Verify the tester on a known source before and after you measure.
- Do not work on the drive while a permanent magnet motor is rotating. A spinning PM motor energises the drive, including its input and output terminals.
- Never tilt the drive. It is heavy, has a high centre of gravity and can topple. All frames have lifting eyes, and R1 to R2 IP21 frames must not be lifted by the cover.
- Skip insulation or voltage withstand tests on the drive itself.
- If auto-reset or restart functions are on, mark the machine, for example “THIS MACHINE STARTS AUTOMATICALLY”, per IEC/EN/UL 61800-5-1.
How long do I wait after power-off, per the ACQ580 manual?
Always wait 5 minutes after you disconnect input power. This lets the DC link capacitors discharge. Then prove the installation dead with your tester.
On ACQ580-04 R10 and R11 modules, use a multimeter with at least 1 Mohm impedance. Confirm the voltage is close to 0 V between the input terminals and the PE busbar, and between UDC+/UDC- and PE. Then fit temporary grounding as local rules require.
Step-by-step: install and start up an ACQ580-01 with the manual
Each step ends with a check. Follow the quick guide for your frame size, and use the hardware manual for full detail. This abb acq580 manual walk-through follows the ACQ580-01 order.

Step 1: Unpack and match the drive to your ACQ580 manual
Keep the drive in its package until you are ready to install it. Then check for transport damage and confirm the contents match your order.
Check: the type code and variant match the ACQ580 hardware manual and firmware manual you downloaded.
Step 2: Reform the capacitors if the drive has been stored
If the drive has not been powered up for a year or more, you must reform the DC link capacitors. Follow ABB’s capacitor reforming instructions or contact ABB technical support. This applies to spare drives on a shelf too.
The equipment, voltage, current and time depend on the drive, so take them from ABB’s reforming instructions for your exact type. Also check the hardware manual for your variant, because the storage interval may differ between variants. Do not copy figures from another drive.
Check: you know the storage date or serial number age, and you have recorded the reforming.
Step 3: Mount the drive
First, mark the holes with the mounting template. Next, remove the template before you mount the drive. Then drill the holes and fit anchors or plugs. Choose fasteners that suit the wall material, the drive weight and the application.
The R3 frame in UL Type 4X NEC types weighs more than 50 lb (23 kg), so use a lifting device. Use the lifting eyes and never tilt the drive.
Check: the drive is level and firmly fixed, with the clearances shown in the hardware manual.
Step 4: Check the grounding system compatibility
You can connect all drives to a symmetrically grounded TN-S system (centre-grounded wye) with no change to the built-in EMC filter or varistors. However, for other systems, such as IT (ungrounded) or corner-grounded TN, reconfigure the EMC and VAR screws. Use the table in the guide.
The screw positions and the limits for each frame size, including R4 and R5 on corner-grounded networks, differ by frame and voltage. Read them from the hardware manual or quick guide for your exact type. Do not guess, because the wrong screw position can damage the drive.
Check: the screw positions match your supply type.
Step 5: Measure insulation resistance
Measure the input cable before you connect it to the drive. Next, measure the motor cable and motor with the cable disconnected from the drive. In each case, measure between each phase conductor and PE using 1000 V DC.
An ABB motor must read above 100 Mohm, referenced at 25 °C (77 °F). For other motors, use the maker’s value. Because moisture lowers the reading, dry the motor and measure again.
Check: you logged the readings before any connection to the drive.
Step 6: Connect power and motor cables
For best EMC performance, ABB recommends symmetrical shielded VFD cable for input power. Use symmetrically shielded VFD cable for the motor too. It reduces bearing current and stress on motor insulation. IEC installs need cable rated for at least 70 °C conductor temperature. In North America, use copper conductors only, and follow the NEC guide.
First, cut the grommet holes to fit. Next, strip the cable to the length shown; R1 and R2 have markings for 8 mm. Then ground the shield 360 degrees under the clamp. Mark the shield pigtail as a PE conductor in yellow-green. Finally, tighten the screws to the torque in the figures.
On IP66 (UL Type 4X) NEC cable boxes, torque the screws to 2.5 Nm (1.8 lbf-ft). Use a hand tool with a Pozidriv #2 bit. Do not use power tools and do not over-torque, or you lose the water-tight seal.
Which cable sizes, fuses and torques apply to each frame?
They change with frame size (R1 to R9) and supply voltage, so use the tables in the technical data chapter of the hardware manual for your type code. Those tables give the fuse and cable sizes and the terminal tightening torques. Do not reuse figures from another frame.
Check: torque is correct, shields are terminated, unused grommets are fitted, and cables are secured outside the unit.
Step 7: Connect control cables per the ACQ580 firmware manual
Wire the control cables for your application. Ground the outer shield 360 degrees under the clamp. Also keep signal wire pairs twisted as close to the terminals as you can, to prevent inductive coupling.
Before you wire the run, permissive and feedback signals, read the default I/O configuration in the firmware manual. It shows which terminal does what for the run command, the permissive, the feedback and the relay outputs. Terminal use depends on the control macro and program version, so wire from the table in your own revision.
Check: the run permissive signal (parameter 20.40) will be active when the drive needs to run.
Step 8: Power up and run the First start assistant
Make sure the installation is complete. Then power up the drive and wake the Hand-Off-Auto control panel. Select Start set-up and press Next. After that, the First start assistant asks for motor and application settings until the panel shows that first start is complete.
Do not power up more than five times in ten minutes. Too many power-ups can damage the DC capacitor charging circuit.
Check: you entered the motor data from the nameplate. On ACQ580-31 and ACQ580-34, also select the supply voltage with parameter 95.01 before the ID run.
Step 9: Prepare for and run the motor ID run from the ACQ580 manual
The ID run lets the drive measure the motor. If you changed any parameter values, the firmware manual requires these limits before the run:
- Set 30.11 Minimum speed below 0 rpm.
- Make 30.12 Maximum speed equal to the motor rated speed.
- Keep 30.17 Maximum current above IHD.
- Hold 30.20 Maximum torque 1 above 50%.
These conditions come from one firmware manual start-up chapter. However, your own revision may differ, so check it.
Vector control mode (99.04) must be selected by hand for PM or SynRM motors (99.03). If the drive is in scalar mode, change it with the Control mode assistant or parameter 99.04. Also confirm the run permissive signal (20.40) is active.
Check: the ID run completes without a fault.
Step 10: Set up the pump control mode and protections
The firmware offers these pumping modes:
- Intelligent pump control (IPC).
- Level control (filling).
- Level control (emptying).
- Single pump control (PC).
- Soft pump control (SPC).
Make extra settings, such as pump protections, under Main menu, Primary settings, Pump protections. In IPC, select pump priority (High, Normal, Low) with parameter 76.77. Pump 1 to 8 running times are parameters 77.11 to 77.18. Finally, ABB recommends reading the pump maker’s instructions for best performance.
Check: the home view shows the expected feedback and frequency, and Hand, Off and Auto all work.
How do I wire and test Safe Torque Off, and set up Modbus control?
For Safe Torque Off (STO), wire the safety circuit to the STO terminals shown in the hardware manual’s STO chapter. Then run the validation test that chapter describes before the machine goes into service. A qualified person must do this, and the result should be recorded.
For building or SCADA control over the embedded fieldbus, use parameter group 58. Set the protocol, then match the node address, baud rate and parity to the master. Next, apply the new settings as the firmware manual describes. After that, set the control source and reference parameters so the drive follows the fieldbus. The fieldbus chapter of the firmware manual lists the register map.
Which ACQ580 manual fits the -04 modules and -31?
Do not use the -01 documents for other variants. The ACQ580-04 has its own hardware manual for 250 to 500 kW, a drive modules quick installation guide, and cabinet design and construction instructions. It shares the pump control firmware manual and quick start-up guide.
The ACQ580-31 has its own hardware manual. ABB lists an ACQ580-31 quick installation guide (3AXD50000049859) and a separate ACQ580-31 drives US quick installation guide (3AXD500000481873). Both use the First start assistant on a Hand-Off-Auto panel. As a result, the link list for your variant is the best way to find the right ACQ580 hardware manual.
What about the -07, -34, -PC/PD, -C01 and irrigation variants?
Each of these has its own page and documents on ABB’s site, so start from that variant’s link list. The ACQ580-PC/PD and -C01 have separate pages. For the ACQ580-PDR, use the ACS580/ACH580/ACQ580-PDR supplement (3AXD50001285388). For US irrigation drives, use the ACQ580 irrigation supplement (3AXD50000885664). The ratings and maximum motor cable lengths are in the technical data of each variant’s own hardware manual, so read them there instead of reusing -01 figures.
Common ACQ580 manual mistakes to avoid
- Using the wrong manual for the variant, or an old firmware manual revision.
- Skipping capacitor reforming on stored or spare drives.
- Not testing insulation, or testing through the drive.
- Over-torquing or using power tools on IP66 cable box screws.
- Setting the EMC and VAR screws wrong for the grounding system.
- Starting the ID run with limits outside the required range.
- Cycling power again and again in a short time.
- Working on the drive with a rotating PM motor, or before the 5 minute wait is over.
When something goes wrong: ACQ580 manual fault tracing and when to call for help
The ACQ580 firmware manual has a fault tracing chapter. Use it with the fault code on the panel. It also covers the control panel, fieldbus control and the parameter list.

What do common ACQ580 fault codes mean?
These codes are common across ABB’s ACS580 family. Treat the first fix as a starting point, and confirm the cause in the fault tracing chapter for your revision.
| Code | Meaning | First fix |
|---|---|---|
| 2310 | Overcurrent | Check the motor load, the motor data and the ramp times. |
| 2330 | Earth leakage | Test the motor and motor cable insulation. |
| 3130 | Input phase loss | Check the supply fuses and input wiring. |
| 3210 | DC link overvoltage | Check the supply voltage and the deceleration time. |
| 3220 | DC link undervoltage | Check the supply voltage and for a missing phase. |
| 4310 | Excess temperature | Check cooling air flow, the fan and ambient temperature. |
| 7121 | Motor stall | Check for a jammed pump and the stall settings. |
Warnings use the same style of codes and show the same problem before it trips the drive. Always remove the cause before you reset.
When should I call for help?
Stop and call for repair or ABB technical support in these cases:
- You do not know the reform status of a stored drive.
- The drive shows damage.
- Insulation readings fail.
- Faults persist after you recheck wiring and parameters.
Precision Electric repairs and supplies drives. First, confirm your model and type code. However, we do not list ACQ580 drives, but our ACS180 and ACS255 lines are nearby ABB options.
Frequently asked questions
Which ABB ACQ580 manual do I need?
Use three documents: the hardware manual for mounting, wiring and technical data, the firmware manual for start-up, parameters and fault tracing, and the quick guide for your variant. For ACQ580-01, the hardware manual is 3AXD50000044862 and the firmware manual is 3AXD50000035867. Pick the IEC or NEC quick guide to match your drive.
Where can I download the ACQ580 manual?
Use ABB’s document library at www.abb.com/drives/documents, or the link lists for your variant, such as the ACQ580-01 and ACQ580-04 manuals pages. Then search by the document code and check the revision.
How long do I wait before working on an ACQ580 after turning off power?
ABB says to wait 5 minutes after you disconnect input power so the DC link capacitors discharge. Then prove the installation dead with a voltage tester. Verify the tester on a known source first.
Do I need to reform the capacitors on a spare ACQ580?
Yes, if the drive has not been powered up for a year or more. Follow ABB’s capacitor reforming instructions or contact ABB technical support.
How do I start up an ACQ580 for the first time?
Finish and check the installation, then power up. On the Hand-Off-Auto panel, select Start set-up, then Next, and enter the motor and application settings until first start is complete. Then do the ID run and set pump control and protections per the firmware manual.
The right ACQ580 user manual set, the safety rules and the ten steps above should get your drive running with fewer surprises. Always match each document to your variant, market and firmware revision. If you need help with a drive, a repair or a quote, contact Precision Electric, or browse our ABB drive products.